Econ Group have been working on a project in Hastings, East Sussex over the past few months. The scheme of works is part of a large housing development for a national housing developer. The site was a former school and old recreational grounds.
Econ were tasked with the removal of the slabs and foundations of the premises. We also had to remove all hard standings and recreational equipment. The concrete and hardcore was crushed on site for reuse on the development.
Resources:1x Site Manager, 4 x CPCS Plant Operators,3 x CCDO Operatives, 1 x Traffic Marshall
Plant:1 x ZX350, 2 X ZX210, 1 X ZX130 Excavators, 1 x 45 Tone Mobile Crusher, 1 x 10Tonne Dumper, 1 x 14 Tonne padfoot roller.
Duration:7 Weeks
"Also evident was the pride the staff have in what they do and the care they take to work safely at all times and offer the best service possible to their clients"