News

Digging in the sand at Hastings!

Econ Group have been working on a project in Hastings, East Sussex over the past few months. The scheme of works is part of a large housing development for a national housing developer. The site was a former school and old recreational grounds.

Econ were tasked with the removal of the slabs and foundations of the premises. We also had to remove all hard standings and recreational equipment. The concrete and hardcore was crushed on site for reuse on the development.

Resources:1x Site Manager, 4 x CPCS Plant Operators,3 x CCDO Operatives, 1 x Traffic Marshall

Plant:1 x ZX350, 2 X ZX210, 1 X ZX130 Excavators, 1 x 45 Tone Mobile Crusher, 1 x 10Tonne Dumper, 1 x 14 Tonne padfoot roller.

Duration:7 Weeks

"I have worked with Econ on many projects within London Underground and Network Rail infrastructure. Econ have always been very proactive in their approach to the projects and have worked collaboratively with my teams from the very early stages. I would definitely recommend them to others"

Morgan Sindall

Our Accreditations

Enabling
Teamwork
Enabling
Health & Safety
Enabling
Excellence
Enabling
Growth

See how we are Enabling the Future
download our new brochure

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.