Econ Group have been working on a project in Hastings, East Sussex over the past few months. The scheme of works is part of a large housing development for a national housing developer. The site was a former school and old recreational grounds.
Econ were tasked with the removal of the slabs and foundations of the premises. We also had to remove all hard standings and recreational equipment. The concrete and hardcore was crushed on site for reuse on the development.
Resources:1x Site Manager, 4 x CPCS Plant Operators,3 x CCDO Operatives, 1 x Traffic Marshall
Plant:1 x ZX350, 2 X ZX210, 1 X ZX130 Excavators, 1 x 45 Tone Mobile Crusher, 1 x 10Tonne Dumper, 1 x 14 Tonne padfoot roller.
Duration:7 Weeks
"We found Econ to be talented and professional. We recently employed them to undertake some regeneration work to help us prepare for the building of our new Queen Elizabeth II Centre. Our experience of working with them was excellent. They were conscientious and efficient when working to a tight deadline and we have no hesitation recommending them for other projects."