Asbestos Removal
Five Days
The removal of 30 linear meters of asbestos insulation to ductwork within roof plant room under fully controlled conditions within fully operational sugar refinery.
The works were carried out within a fully controlled negative pressure enclosure using wet stripping techniques from a safe strip machine to suppress the sectional insulation using surfactant from a sprayer attachment and the wrap and cut methodology. All works were carried out within a 5 day programme and the enclosure subject to a 4 stage re occupation certificate by the clients nominated analytical company.
ARCA Trained Asbestos Managers through to Operatives, Econ’s team included staff who met the following requirements: SMSTS, SSSTS, CPCS, and CCDO
Econ’s Waste Lorries from 18t Skip lorries to 32t Roro Skip Lorries & all plant in association with the Asbestos Removal.
Econ Group Ltd are very efficient with response and communication. They have always responded very quickly to any jobs that I have sent to them and report back with a full report including photos. I would highly recommend using Econ Group.