Case Study

DATE

July 7, 2020

LOCATION

Sugar Refinery

DIVISONS

Licensable Asbestos Removal - Roof Void

Services

Asbestos Removal

Project duration

Five Days

Summary

The removal of 30 linear meters of asbestos insulation to ductwork within roof plant room under fully controlled conditions within fully operational sugar refinery.

The works were carried out within a fully controlled negative pressure enclosure using wet stripping techniques from a safe strip machine to suppress the sectional insulation using surfactant from a sprayer attachment and the wrap and cut methodology. All works were carried out within a 5 day programme and the enclosure subject to a 4 stage re occupation certificate by the clients nominated analytical company.

Staffing requirements

ARCA Trained Asbestos Managers through to Operatives, Econ’s team included staff who met the following requirements: SMSTS, SSSTS, CPCS, and CCDO

Equipment/Plant Used

Econ’s Waste Lorries from 18t Skip lorries to 32t Roro Skip Lorries & all plant in association with the Asbestos Removal.

Tags

No items found.

Similar Case Studies

In short, the service received by yourselves has been faultless in terms of works carried out for London Bridge DU. The response times in emails as well as getting to site to do the works is very efficient, and should there be any issues, the communication from all at Econ who I’ve dealt with has been professional. Thank you,

Waste & Fly Tipping Sept 2023

Our Accreditations

Enabling
Teamwork
Enabling
Health & Safety
Enabling
Excellence
Enabling
Growth

Subscribe to our Newsletter!

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.