Asbestos Removal
Five Days
The removal of 30 linear meters of asbestos insulation to ductwork within roof plant room under fully controlled conditions within fully operational sugar refinery.
The works were carried out within a fully controlled negative pressure enclosure using wet stripping techniques from a safe strip machine to suppress the sectional insulation using surfactant from a sprayer attachment and the wrap and cut methodology. All works were carried out within a 5 day programme and the enclosure subject to a 4 stage re occupation certificate by the clients nominated analytical company.
ARCA Trained Asbestos Managers through to Operatives, Econ’s team included staff who met the following requirements: SMSTS, SSSTS, CPCS, and CCDO
Econ’s Waste Lorries from 18t Skip lorries to 32t Roro Skip Lorries & all plant in association with the Asbestos Removal.
Orpington Maintenance Delivery Unit have been utilising Econ’s Services since the commencement of the new Environmental Services contract in October 2021. Since mobilisation Econ have provided our DU with a very efficient and professional service. The customer service and contract team are very friendly and approachable. I use the services of Econ primarily for Non-Emergency call outs which includes both general litter picking and fly tipping jobs as well as larger and more complex waste issues. Every job that I raise is acknowledged and responded to within a quick timescale. Following the completion of each job, I receive a signed completion certificate including photos and detailed commentary. Similarly the period payment reporting is issued on time with full back up information for ease of reference. This enables us to identify jobs and authorise payment quickly. I can strongly recommend the services of Econ who have improved the levels of service previously experienced and assisted our team with the resolution of a number of more difficult and costly cases on our patch.