Enabling Works Package - Principle Contractor
10 months
Econ were contracted to carry out the complete enabling works package at Tate & Lyle, we carried out all the design works, service isolations and diversion, all surveys including Ground Radar & Demolition Asbestos Surveys.
We also liaised and gained consents from all the local and statutory authorities.
We then proceeded to remove all contaminated materials including Asbestos, we decommissioned all the redundant plant and demolished the site to ground level.
Econ’s team included staff who met the following requirements: CSCS, CPCS, CCDO, Licensed Asbestos Removal.
High reach excavators, crushers, telehandlers, loading shovels, bobcats.
Senior Project Manager
“We were impressed with the approach used by you operation team to carry out the works both professional and diligently. Econ were very accommodating to meet our needs from the initial presentations prepared on strategy to mitigate risks and throughout execution of the works and keeping us fully informed and giving us the confidence we needed. The approach of Econ Site supervisors and visiting managers through to operatives on site was always of a high standard and good-natured and we are pleased to give credit where it is due. On site initiatives by the team from demonstrations /videos of emergency procedures when working in asbestos enclosures and working with consistent site uniforms contributed to the site achieving a Kier ‘Blue’ for best practice and working above standards. This was an excellent example of collaborative working and a joint approach to promptly overcome some of the challenges with asbestos and how best to deal with this along with working near challenging neighbours’ properties, the school and the church.”