Case Study

DATE

June 28, 2020

LOCATION

Kings Cross

DIVISONS

Coram Fields

Services

Asbestos Removal and Demolition

Project duration

Four Months

Summary

Econ Construction undertook the role of principle contractor to carry out Asbestos Removal and Demolition of former swimming pool, Stores and plant room in an operational school campus.  The buildings to be demolished were constructed in 1902 and used previously as a hospital and mortuary in its early years.  The structures to be demolished were in close proximity to a Grade II listed wall that bordered the site and Brunswick square gardens and this was protected throughout the works using a protection scaffold cantilevered from the inside of the structures to be demolished.

The demolition works were carried out using careful hand demolition and mechanical demolition to ensure that the listed wall was not damaged at any stage of the works and that noise pollution and vibration was minimised during the project to ensure that students were not disrupted during the project.

Activities Undertaken

- Liaison with Local Authority and local community prior to works including the arranging of permits and licenses to carry out the works.
- Installation of security hoardings.
- GRP Ground Radar Survey of existing services.
- Pre-condition survey of Grade II listed wall.
- Asbestos Refurbishment and Demolition surveys and subsequent removal of hazardous materials from structures to be demolished.
- Asbestos removal using in house staff.
- Isolation and diversion of existing services.
- Temporary works design for the installation of temporary works and demolition design sequencing for structures to be demolished.
- Installation of protective scaffold to listed structures and to protect public interface within park throughout the works.
- Soft strip of all structures prior to demolition.
- Vibration and dust monitoring throughout works.
- Concrete cutting at separation points between structures to be retained and structures to be demolished.
- Demolition of structures using a variety of careful hand demolition and mechanical demolition.
- Removal of slabs and foundations to former structures
- Recycling of arising materials
- Installation of pilling matt.

These works were carried out to budget and programme with no disruption to the operational school campus or users of Brunswick gardens.

Staffing requirements

Full time Project Manager, Quantity Surveyor, Site Manager. Econ’s team included staff who met the following requirements: SSTS, CCDO and CPCS

Equipment/Plant Used

Mobile Elevated Working Platforms, 15t & 8t Demolition Excavator with Various Attachments

Similar Case Studies

“We were impressed with the approach used by you operation team to carry out the works both professional and diligently. Econ were very accommodating to meet our needs from the initial presentations prepared on strategy to mitigate risks and throughout execution of the works and keeping us fully informed and giving us the confidence we needed. The approach of Econ Site supervisors and visiting managers through to operatives on site was always of a high standard and good-natured and we are pleased to give credit where it is due. On site initiatives by the team from demonstrations /videos of emergency procedures when working in asbestos enclosures and working with consistent site uniforms contributed to the site achieving a Kier ‘Blue’ for best practice and working above standards. This was an excellent example of collaborative working and a joint approach to promptly overcome some of the challenges with asbestos and how best to deal with this along with working near challenging neighbours’ properties, the school and the church.”

Demolition and Asbestos Removal Sept 2023

Our Accreditations

Enabling
Teamwork
Enabling
Health & Safety
Enabling
Excellence
Enabling
Growth

Subscribe to our Newsletter!

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.