Demolition
2 Weeks including a Full Weekend Closure
Econ were employed as a principle Contractor to plan, design and remove the canopy outside Woking Railway Station.
Econ started the design phase 18 months prior to the removal.
Econ managed all the liaison and approvals from Network Rail as the canopy removal had direct impact on the operational railway.
Econ carried out the removal of Photovoltaic glass during night time road closures. We then dismantled the canopy during a full weekend closure.
The works progressed whilst the Railway Station stayed fully operational
A full Crane team utilising the Mobile Tower Crane, Econ Demolition Site Managers rotated on shifts, Site Supervisors and Demolition Labourers. Econ’s team included staff who met the following requirements: CCDO, CPCS, IPAF & Hot Cutting
Mobile Telescopic Tower Crane, Mobile Elevated Working Platforms, Debris Netting, 25t Excavator with Selecta Grab attachment, Bulker Lorries for the removal of the materials.
"Also evident was the pride the staff have in what they do and the care they take to work safely at all times and offer the best service possible to their clients"