Demolition
2 Weeks including a Full Weekend Closure
Econ were employed as a principle Contractor to plan, design and remove the canopy outside Woking Railway Station.
Econ started the design phase 18 months prior to the removal.
Econ managed all the liaison and approvals from Network Rail as the canopy removal had direct impact on the operational railway.
Econ carried out the removal of Photovoltaic glass during night time road closures. We then dismantled the canopy during a full weekend closure.
The works progressed whilst the Railway Station stayed fully operational
A full Crane team utilising the Mobile Tower Crane, Econ Demolition Site Managers rotated on shifts, Site Supervisors and Demolition Labourers. Econ’s team included staff who met the following requirements: CCDO, CPCS, IPAF & Hot Cutting
Mobile Telescopic Tower Crane, Mobile Elevated Working Platforms, Debris Netting, 25t Excavator with Selecta Grab attachment, Bulker Lorries for the removal of the materials.
In short, the service received by yourselves has been faultless in terms of works carried out for London Bridge DU. The response times in emails as well as getting to site to do the works is very efficient, and should there be any issues, the communication from all at Econ who I’ve dealt with has been professional. Thank you,