Case Study

DATE

June 30, 2020

LOCATION

Redhill

DIVISONS

Warwick School Redhill

Client

Kier Construction


Location

Redhill


Service

Earthworks and Piling Mat

Halfway through the demolition works on phase 1 we were successfully awarded the groundworks package. This involved a 3 meter reduced dig and then installation of a piling mat in 200mm layers.

The area was a 3000m2 areas with a 1000mm deep piling mat.

We supplied an engineer to set out the levels to suit the client’s construction requirements.

We excavated three meters down across the area, transported and stockpiled the excavated material. Following this, on three sides, we constructed a 45 degree batter.

We then compacted the ground using a ride on roller, layered in 6f5 and geo-grid in 200mm layers up to 1m.

An independent engineer then carried out compaction tests on completion.

Similar Case Studies

“On reactive and response maintenance our Reactive team believe in supporting our customers from start to finish with whatever challenges our thrown at them, dealing with any problems quickly, safely and efficiently’’.

Danny Cheriton – Econ Contracts Director

Danny Cheriton – Econ Contracts Director

Our Accreditations

Enabling
Teamwork
Enabling
Health & Safety
Enabling
Excellence
Enabling
Growth

Subscribe to our Newsletter!

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.