Decommissioning of Redundant Electrical Sub-Station
4 Weeks
Econ were contracted to remove asbestos and demolish a redundant UKPN sub-station. The site covered over 4000 m2
Works involved removing all the asbestos from the switchgear, removing and disposing of the redundant plant, cable and concrete structures.
Works were completed within the required programme with no accidents or incidents.
Staff undertook site specific inductions and all staff were Asbestos and Demolition trained. All machine operators held CPCS qualifications.. Econ’s team included staff who met the following requirements: CCDO, CCDO Burning Operatives and IPAF Operatives
25t 360 Excavator, Articulated Booms, Oxy/Propane Cutting Equipment, Recipriocating Saws, Low Loaders, Skip Lorries, Ekki Mats for Protection of remaining assets and telehandler.
"I have worked with Econ on many projects within London Underground and Network Rail infrastructure. Econ have always been very proactive in their approach to the projects and have worked collaboratively with my teams from the very early stages. I would definitely recommend them to others"