Case Study

DATE

July 7, 2020

LOCATION

Chalton

DIVISONS

Redundant Electrical Sub Station

Services

Decommissioning of Redundant Electrical Sub-Station

Project duration

4 Weeks

Summary

Econ were contracted to remove asbestos and demolish a redundant UKPN sub-station. The site covered over 4000 m2

Works involved removing all the asbestos from the switchgear, removing and disposing of the redundant plant, cable and concrete structures.

Works were completed within the required programme with no accidents or incidents.

Staffing requirements

Staff undertook site specific inductions and all staff were Asbestos and Demolition trained. All machine operators held CPCS qualifications.. Econ’s team included staff who met the following requirements: CCDO, CCDO Burning Operatives and IPAF Operatives

Equipment/Plant Used

25t 360 Excavator, Articulated Booms, Oxy/Propane Cutting Equipment, Recipriocating Saws, Low Loaders, Skip Lorries, Ekki Mats for Protection of remaining assets and telehandler.

Similar Case Studies

In short, the service received by yourselves has been faultless in terms of works carried out for London Bridge DU. The response times in emails as well as getting to site to do the works is very efficient, and should there be any issues, the communication from all at Econ who I’ve dealt with has been professional. Thank you,

Waste & Fly Tipping Sept 2023

Our Accreditations

Enabling
Teamwork
Enabling
Health & Safety
Enabling
Excellence
Enabling
Growth

Subscribe to our Newsletter!

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.