Asbestos Removal
3 days
Econ were instructed to remove sectional pipe insulation containing asbestos from a toilet block at Railway Station. The works were undertaken over a weekend period. All works were undertaken in fully controlled conditions as the material was licensable. The works were carried out in a full enclosure placed under negative pressure.
We pre-arranged for an ARCA audit to be undertaken on site (as part of our continuing site monitoring regime). This passed with no major or minor non conformities.
1 site supervisor and 3 asbestos operatives. Econ’s team included staff who met the following requirements: Full Category C Asbestos training, CSCS Cards, PASMA and First Aid Training.
Negative pressure unit (2300), Wet Strip Injection Unit, Twin Shower Decontamination Unit, 16 Yard Asbestos Skip.
"We found Econ to be talented and professional. We recently employed them to undertake some regeneration work to help us prepare for the building of our new Queen Elizabeth II Centre. Our experience of working with them was excellent. They were conscientious and efficient when working to a tight deadline and we have no hesitation recommending them for other projects."