Case Study

DATE

July 7, 2020

LOCATION

Railway Station

DIVISONS

Licensable Asbestos Removal Toilet Block

Services

Asbestos Removal

Project duration

3 days

Summary

Econ were instructed to remove sectional pipe insulation containing asbestos from a toilet block at Railway Station. The works were undertaken over a weekend period. All works were undertaken in fully controlled conditions as the material was licensable. The works were carried out in a full enclosure placed under negative pressure.

We pre-arranged for an ARCA audit to be undertaken on site (as part of our continuing site monitoring regime). This passed with no major or minor non conformities.

Staffing requirements

1 site supervisor and 3 asbestos operatives. Econ’s team included staff who met the following requirements: Full Category C Asbestos training, CSCS Cards, PASMA and First Aid Training.

Equipment/Plant Used

Negative pressure unit (2300), Wet Strip Injection Unit, Twin Shower Decontamination Unit, 16 Yard Asbestos Skip.

Tags

No items found.

Similar Case Studies

"We found Econ to be talented and professional. We recently employed them to undertake some regeneration work to help us prepare for the building of our new Queen Elizabeth II Centre. Our experience of working with them was excellent. They were conscientious and efficient when working to a tight deadline and we have no hesitation recommending them for other projects."

Coram

Our Accreditations

Enabling
Teamwork
Enabling
Health & Safety
Enabling
Excellence
Enabling
Growth

Subscribe to our Newsletter!

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.