Asbestos Removal
Five Days
The removal of 30 linear meters of asbestos insulation to ductwork within roof plant room under fully controlled conditions within fully operational sugar refinery.
The works were carried out within a fully controlled negative pressure enclosure using wet stripping techniques from a safe strip machine to suppress the sectional insulation using surfactant from a sprayer attachment and the wrap and cut methodology. All works were carried out within a 5 day programme and the enclosure subject to a 4 stage re occupation certificate by the clients nominated analytical company.
ARCA Trained Asbestos Managers through to Operatives, Econ’s team included staff who met the following requirements: SMSTS, SSSTS, CPCS, and CCDO
Econ’s Waste Lorries from 18t Skip lorries to 32t Roro Skip Lorries & all plant in association with the Asbestos Removal.
“We were impressed with the approach used by you operation team to carry out the works both professional and diligently. Econ were very accommodating to meet our needs from the initial presentations prepared on strategy to mitigate risks and throughout execution of the works and keeping us fully informed and giving us the confidence we needed. The approach of Econ Site supervisors and visiting managers through to operatives on site was always of a high standard and good-natured and we are pleased to give credit where it is due. On site initiatives by the team from demonstrations /videos of emergency procedures when working in asbestos enclosures and working with consistent site uniforms contributed to the site achieving a Kier ‘Blue’ for best practice and working above standards. This was an excellent example of collaborative working and a joint approach to promptly overcome some of the challenges with asbestos and how best to deal with this along with working near challenging neighbours’ properties, the school and the church.”