Case Study

DATE

July 7, 2020

LOCATION

Wanstead

DIVISONS

Bush Road Bridge

Services

Bridge Demolition

Project duration

20 hour possession

Summary

Econ spent the week leading up to the possession making sure all the plant and materials were delivered to site in readiness for the possession start time. The plant and materials get checked and re checked. Spare machines are available on site just encase an item of equipment fails.

When the area was officially handed over to Econ to commence the track protection was installed and checked.

Next phase of the works was to position the excavators and start to demolish the bridge down to the pre-determined cut lines. All demolition arising’s were removed during the demo works and cleared to an area to be stockpiled until the tipper lorry’s came to site in the morning to start clearing. All track protection removed and restored ready to be collected. All machines cleaned down and made ready for transport back to Econ depot.

All works were completed in under two shifts. All the site arising’s were removed from site and disposed of in an environmentally responsible way. Two team members then remained on site for a further three days to see the materials and plant off site.

Staffing requirements

Working in a railway environment requires a high degree of health and safety knowledge and expertise and the use of suitably qualified and accredited personnel to carry out the works. Each shift had One manager and One director from the company on site to oversee their assigned shift. Econ’s team included staff who met the following requirements: CSCS, Banksman, Machine operators, Sentinel approved and registered work force, CCDO, CPC.

Equipment/Plant Used

3 x 25 tonne excavators, 3 x high dreamers, 1 x 35 tonne excavator, 2 x 14 tonne excavators. Ekki mats and cordek polystyrene blocks.

Similar Case Studies

“On reactive and response maintenance our Reactive team believe in supporting our customers from start to finish with whatever challenges our thrown at them, dealing with any problems quickly, safely and efficiently’’.

Danny Cheriton – Econ Contracts Director

Danny Cheriton – Econ Contracts Director

Our Accreditations

Enabling
Teamwork
Enabling
Health & Safety
Enabling
Excellence
Enabling
Growth

Subscribe to our Newsletter!

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.