Case Study

DATE

July 7, 2020

LOCATION

Barking

DIVISONS

Barking Riverside Extension Project

Services

Redundant Rolling Stock Disposal

Project duration

Four and a half weeks including Three Weekend Possessions.

Summary

Econ have been contracted for the Disposal of Redundant Rolling Stock.

The works have included removal of asbestos and then breaking up and disposal of 25 rolling stock units from a Rail locked work site in London.

Works have now been completed a week early with three weekend 47 hour possessions carried out in total.

The teams worked very hard to deliver these works safely and within program. We would like to thank all teams involved for their hard work and professionalism during these works.

Staffing requirements

Asbestos Trained Staff, CCDO Demolition Operatives, CCDO Burning Operatives, CPCS Plant Operators, Network Rail COSS, RRV POS, RRV COSS, RRV Machine Controllers. Econ’s team included staff who met the following requirements: CPCS, CSCS, CCDO, COSS.

Equipment/Plant Used

RRV (DX270 with Grab & 4 x Box Trailers), 14t Demolition Excavator, 25t Demolition Excavator, 35t Demolition Excavator, all with Selecta Grab, Breakers and Shears and Oxy/Propane Burning Equipment.

Similar Case Studies

"I have worked with Econ on many projects within London Underground and Network Rail infrastructure. Econ have always been very proactive in their approach to the projects and have worked collaboratively with my teams from the very early stages. I would definitely recommend them to others"

Morgan Sindall

Our Accreditations

Enabling
Teamwork
Enabling
Health & Safety
Enabling
Excellence
Enabling
Growth

Subscribe to our Newsletter!

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.