Case Study

DATE

July 7, 2020

LOCATION

Barking

DIVISONS

Barking Riverside Extension Project

Services

Redundant Rolling Stock Disposal

Project duration

Four and a half weeks including Three Weekend Possessions.

Summary

Econ have been contracted for the Disposal of Redundant Rolling Stock.

The works have included removal of asbestos and then breaking up and disposal of 25 rolling stock units from a Rail locked work site in London.

Works have now been completed a week early with three weekend 47 hour possessions carried out in total.

The teams worked very hard to deliver these works safely and within program. We would like to thank all teams involved for their hard work and professionalism during these works.

Staffing requirements

Asbestos Trained Staff, CCDO Demolition Operatives, CCDO Burning Operatives, CPCS Plant Operators, Network Rail COSS, RRV POS, RRV COSS, RRV Machine Controllers. Econ’s team included staff who met the following requirements: CPCS, CSCS, CCDO, COSS.

Equipment/Plant Used

RRV (DX270 with Grab & 4 x Box Trailers), 14t Demolition Excavator, 25t Demolition Excavator, 35t Demolition Excavator, all with Selecta Grab, Breakers and Shears and Oxy/Propane Burning Equipment.

Similar Case Studies

“We were impressed with the approach used by you operation team to carry out the works both professional and diligently. Econ were very accommodating to meet our needs from the initial presentations prepared on strategy to mitigate risks and throughout execution of the works and keeping us fully informed and giving us the confidence we needed. The approach of Econ Site supervisors and visiting managers through to operatives on site was always of a high standard and good-natured and we are pleased to give credit where it is due. On site initiatives by the team from demonstrations /videos of emergency procedures when working in asbestos enclosures and working with consistent site uniforms contributed to the site achieving a Kier ‘Blue’ for best practice and working above standards. This was an excellent example of collaborative working and a joint approach to promptly overcome some of the challenges with asbestos and how best to deal with this along with working near challenging neighbours’ properties, the school and the church.”

Demolition and Asbestos Removal Sept 2023

Our Accreditations

Enabling
Teamwork
Enabling
Health & Safety
Enabling
Excellence
Enabling
Growth

Subscribe to our Newsletter!

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.